Bespoke project management for the self builder and small developer






A detailed programme will form the backbone of the self build project or small development and ensures that the agreed completion date is met.

  • It must show each discipline (trade) and how they interact with start dates and follow on trades shown
  • It must identify a critical path eg: foundation completion, watertight completion, services completion etc
  • It must highlight delivery dates of long lead items and specialised products
  • It must highlight staged completion dates so as to accomodate specialised deliveries or trades
  • It must be capable of being monitored against actual progress and against the cashflow forecast
  • It must be easily and readily updated to all parties if circumstances change or client changes are made
A contract with any builder should always include a programme agreed with all parties.